Project

Fuels Terminal Upgrade – Ethanol Blending

Turnkey project to upgrade existing conventional fuels terminal to facilitate ethanol blending requirements per the Alberta Renewable Fuels Standard (RFS) regulations requiring a pooled average of 5% ethanol in fuels.

Location
Edmonton, AB
Industry
Energy
Client
Suncor Energy
Challenge

Meeting Regulatory Deadline & Zero Impact on Terminal Operations

The key challenge of the project was related to the fast tracked nature of scheduling due the firm regulatory deadline. The project was also challenged to have zero impact to day-to-day operations at the terminal which is one of the busiest terminals in North America.

Outcome

Value Engineering and Efficient Subcontractor Management

The project scope was developed with client with a number of value engineering elements resulting in significant cost savings and schedule savings. During Construction, TWD managed 6 subcontractors with concurrent and competing schedules. The project was delivered on time with a good safety record.

Result
4MML/day
Of terminal throughput.
8,000 BBLS
The project involves the installation of two new 8,000 BBLS ethanol storage tanks.
0
Impact to day-to-day operations terminal.